Week 7 has been a very busy week. I have been helping everyone catch up on their work, from putting load and time tickets into the log and preparing submittals to send to Barton Malow Hunt White. Also I helped Spencer with some NCR’S, organizing them and putting them in the log. Box is becoming a daily thing updating pre tasks and daily reports. Some more preparation on building AB has started Western Mechanical is finishing up on installing plumbing on the main floor and Edgewood installed electrical on the second floor. Now with everything installed Ideal has started laying down re steel on top of the decking for the concrete pours. On the finishing side Ideal had just finished erecting the stairs on the center core.
Here is some of Ideals Iron workers installing the Re Steel on top of the decking.