Ideal Contracting was awarded the contract for a new banking facility on Eight-mile and Woodward in Detroit, Michigan. The construction of the new bank was designed to relocate and replace an existing branch on Dequindre Road.

The project began with the demolition of two existing buildings to make way for the construction of the new 3,650 SF branch. However, due to the number of buildings and additions to those buildings, there were four electrical services, three water services, and three gas services that needed to be removed. This presented a challenge in obtaining several demolition clearance letters. An additional concern that Ideal had to overcome was the location of the project being in an area with a high homeless population. To prevent disruptions to the project, Ideal Contracting closely monitored tools and equipment while maintaining the safety of all job site personnel.

One of the many features of this bank is its advanced security vestibule that uses access technology in conjunction with metal detectors to keep the staff and customers safe. The vestibule had to be constructed outside of the building and then subsequently rolled into place to be tied into the facility.

Throughout the project, Ideal Contracting managed 17 subcontractors and 8 owner subcontractors. Ideal self-performed all civil, steel, and concrete work for the project which consisted of removing 4,700 yards of dirt, pouring 225 yards of concrete, and the installation of a 90 ft x 30 ft underground detention system. In total, the project was completed with 20,101 manhours, over 6,000 of them being for Ideal’s self-perform work. The project started in November 2021 and was completed in September 2022 with high praise from the owner. The branch was opened to the public shortly after project completion.

December 2, 2022

New Banking Facility

Ideal Contracting was awarded the contract for a new banking facility on Eight-mile and Woodward in Detroit, Michigan. The construction […]
March 24, 2020

General Motors Estes-Cole Pedestrian Connector

General Motors selected Ideal Contracting as the design-build contractor for the Estes-Cole Pedestrian Connector project at the Global Tech Center. […]
October 25, 2019

GM Building 31 Emissions Sustainment Phase 2

Ideal Contracting was awarded the General Motors Building 31 Emissions Sustainment project which consisted of the build-out of (4) new […]
August 24, 2019

Ghafari Building One Renovation

Ghafari Associates awarded Ideal with the second-floor renovation of its world headquarters located in Dearborn, Michigan.  The 21,000-square-foot interior office […]
August 22, 2019

Marathon Rail Spur Project

Ideal Contracting was awarded four individual bid packages which consisted of the site work, foundations, steel fabrication, and installation of […]
August 22, 2019

GM Building 31 Office Renovation

The Building 31 Office Renovation project included the demolition and renovation of 37,500-square-feet of office space. The scope of work […]
August 22, 2019

GM Asset Sustainment

Ideal Contracting was awarded the Asset Sustainment project at the Global Tech Center in Warren, MI. The scope included removal […]
August 22, 2019

Toyota Powertrain Lab Expansion Phase 2

The Toyota Powertrain Expansion Phase 2 project was one of the final projects in Toyota’s 4-year corporate realignment.  It provided […]
August 22, 2019

Toyota R + D Calty Design Studio Expansion

Ideal Contracting was awarded the general contracting package for the Research & Development Calty Design Studio Expansion. The purpose of […]