Bluewater Compressor Station

Project
At a glance

Project Overview:

The Bluewater Gas Storage project includes a new compressor designed to increase Bluewater’s operating pressure.

Ideal Contracting is self-performing the excavation and concrete work for this project. The scope includes earthwork, fencing, laydown areas, concrete foundations, landscaping, and soil erosion control measures. Approximately 1,537 CY of concrete was placed for the foundations, 53,000 tons of fill material was imported to construct on site building pads and berms, 2,000 LF of electrical trench was excavated and backfilled for underground electrical.

The project commenced in August of 2020 and will be completed in June of 2021.